CTA Sets Monday Deadline For OmniTrax

The Canadian Transportation Agency has told OmniTrax that it has until Monday to show that they are complying with a recent order, or else.

 

The CTA ordered the Hudson Bay Railway, which is owned by OmniTrax, to start the process of repairing the rail link to Churchill by July 3rd .

 

The agency says however that their preliminary view is that HBR has failed to

comply with the order, and that the CTA should establish specific deadlines for

compliance steps.

 

A report from OmniTrax says that they issued a request for proposal to six pre-screened contractors on June 28 th , though they have not commented on whether or not they have received any bids.

 

The CTA has said that the Denver-based Corporation is ignoring the fact that

their order made it clear that financial circumstances do not release the company from its service obligations.

 

Visitor Poll

How many trick-or-treaters do you typically get a year?
Add a Comment
(Fields are Optional)

Your email address is never published.

Weather

"Your" Calendar

October

S M T W T F S
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30 31