An old resolution will be brought back to the next council meeting after Councillor Duncan Wong rescinded resolution # 2016 250.

 

The resolution which was passed at the December 12th meeting approved the additional cost of just over $147 thousand to JR Cousin which was the project manager for Phase 4 work at the Waste Disposal Grounds.

 

The additional cost was paid out because of the extra excavation costs and management costs that were originally not considered in the project.

 

The extra costs come from the clay cut-off wall between Phase 1 and Phase 4 being twice as deep as anticipated.

 

Because of the rescinding, the resolution will once again be looked at the January 16th meeting, and will go through another vote.

 

Hide Comments


Quick Pick

 



Weather



Visitor Poll

Are you concerned about forest fires in our area?
Yes. It's so dry and we're surrounded by trees.
Not really. One good rain and we'll be fine.
Add a Comment
(Fields are Optional)
Name:
Email:
Your email address is never published.
View Results


"Your" Calendar


LinkedUpRadio Envisionwise Web Services